On behalf of ARGE SuedLink Lot 6, consisting of the companies Max Bögl and Michels Trenchless GmbH, Heitkamp Energy Infra GmbH is carrying out the trenchless laying of approx. 22,180 m of cable conduits.

The project comprises seven launch pits, from each of which four parallel boreholes with lengths between 380 and 1,600 meters will be drilled. Construction is scheduled to start in 2026, with work lasting 22 months until the end of 2027.